shortcourse
Can anyone answer this?
name 2 supply characteristics that can only be be confirmed by enquiry. Note the only
general concensus was that everything can be measured, even lecturer was shaking his head.
If there was no supply actually connected, different question, but it did not say that.
Help required.Typical city and guilds confusion. All the guys were very unhappy.
Name 10 things that need veryfying on a sealed consumer unit before inpection and testing commences. 10 Point Question
Next question. name 5 additional things that need veryfying on earthing and bonding on same circuit. 5 point question
Diagram and description of testing of earth rod resistance on generator supplying back up supply for data protection.
Why does one end of a bonding conductor need to be disconeccted before continuity testing 6 Point question
What more than parallel paths ?
I think most guys are preparing for a resit in February.
Hope this helps anyone preaparing for 2395
name 2 supply characteristics that can only be be confirmed by enquiry. Note the only
general concensus was that everything can be measured, even lecturer was shaking his head.
If there was no supply actually connected, different question, but it did not say that.
Help required.Typical city and guilds confusion. All the guys were very unhappy.
Name 10 things that need veryfying on a sealed consumer unit before inpection and testing commences. 10 Point Question
Next question. name 5 additional things that need veryfying on earthing and bonding on same circuit. 5 point question
Diagram and description of testing of earth rod resistance on generator supplying back up supply for data protection.
Why does one end of a bonding conductor need to be disconeccted before continuity testing 6 Point question
What more than parallel paths ?
I think most guys are preparing for a resit in February.
Hope this helps anyone preaparing for 2395