C
claypole
Firstly a huge thanks to all the regular contributors on here and other boards for a first class education on all things solar pv. As a mere consumer with no spark qualification I'm almost certainly about to lay myself open to be shot down in flames but the ramifications if I'm correct are significant so here goes anyway.
Take a typical solar pv install with a nominal 3kwp array, and an inverter certified G83/1 compliant and certified max ouput 3kw. In other words, regardless of your personal preference for defining TIC, DNC etc this will any way up fall easily within G83/1 relaxation and 1st FIT band rate (assuming it's the only generator on site.)
My clear understanding is that whilst this obviates you of the need to make any pre-application to the DNO you MUST nevertheless notify the DNO within 28 days of install using an "Installation Commissioning Confirmation" form (G83/1-1 Appendix 3).
During conversation with an experienced insataller, with many pv installs under the belt, it became apparent that his equally clear view was that this was not necessary. His only registration was with MCS and that satisfied the requirements. I just don't see how this can be? I've located the Ofgem FIT register guide and even downloaded the register data for 2010 and nowhere can I see any mention of the DNO. You might argue that the FIT application would take care of this but I presume this could be made to any supplier, not necessarily within the relevant DNO and in any event the customer for whatever reason might not make a FIT application. Am I missing something? Comments please, but don't knock me down too hard. (And apologies to the installer concerned - no offence intended just wanting to canvas further opinion and perhaps discover what I'm missing)
Take a typical solar pv install with a nominal 3kwp array, and an inverter certified G83/1 compliant and certified max ouput 3kw. In other words, regardless of your personal preference for defining TIC, DNC etc this will any way up fall easily within G83/1 relaxation and 1st FIT band rate (assuming it's the only generator on site.)
My clear understanding is that whilst this obviates you of the need to make any pre-application to the DNO you MUST nevertheless notify the DNO within 28 days of install using an "Installation Commissioning Confirmation" form (G83/1-1 Appendix 3).
During conversation with an experienced insataller, with many pv installs under the belt, it became apparent that his equally clear view was that this was not necessary. His only registration was with MCS and that satisfied the requirements. I just don't see how this can be? I've located the Ofgem FIT register guide and even downloaded the register data for 2010 and nowhere can I see any mention of the DNO. You might argue that the FIT application would take care of this but I presume this could be made to any supplier, not necessarily within the relevant DNO and in any event the customer for whatever reason might not make a FIT application. Am I missing something? Comments please, but don't knock me down too hard. (And apologies to the installer concerned - no offence intended just wanting to canvas further opinion and perhaps discover what I'm missing)
Last edited by a moderator: