Hi Guys
Sorry if this seems an old subject but its new to me. When I first started looking into PV I was informed that :
Do your first install then get your MCS done. Then when your customer registers for the feed in tariff the start date for 1st payment will be back dated to commission date of installation.
Install/Commission of system 15th April
MCS inspection 13th May
MCS certificate issued 8th June. I tried to register job with intallation date 15/4 but could only enter 8/6 as earliest date.
Customer applies to DNO 5th July only to be told that when DNO received the returned fit application form and MCS cert. would they start the tariff date and generation meter reading.
Apologies if this seems long winded but I am trying to get the facts out. Does this sound correct? My customer has missed out on 11 weeks of tariff. I feel I misled them as I had been given the wrong info myself.
Any comments/advice appreciated.
Sorry if this seems an old subject but its new to me. When I first started looking into PV I was informed that :
Do your first install then get your MCS done. Then when your customer registers for the feed in tariff the start date for 1st payment will be back dated to commission date of installation.
Install/Commission of system 15th April
MCS inspection 13th May
MCS certificate issued 8th June. I tried to register job with intallation date 15/4 but could only enter 8/6 as earliest date.
Customer applies to DNO 5th July only to be told that when DNO received the returned fit application form and MCS cert. would they start the tariff date and generation meter reading.
Apologies if this seems long winded but I am trying to get the facts out. Does this sound correct? My customer has missed out on 11 weeks of tariff. I feel I misled them as I had been given the wrong info myself.
Any comments/advice appreciated.