A

adam.h

Ok, installing a new cu, leaving old one in place. They currently have 60A main fuse. With the new demand added the total MD is now 86A.

Do I just ring up the supplier and get them to change the fuse and meter tails to 25mm where needed. Can I then keep the 16mm out of the henley block to each cu as individually they are lower then 60A?
Will this be a cost to the customer or do the suppliers pay for this?

thaaanks!
 
You would reallly need to speak to the DNO about the propsed changes upgrade of tails is the customers responsibility the DNO stops at the meter unless as some do an isolator is put in then it would be the customers responsibility from isolator to CU.


Chris
 

Similar threads

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
maximum demand, main fuse and tails
Prefix
N/A
Forum
Australia
Start date
Last reply date
Replies
2
Unsolved
--

Advert

Thread statistics

Created
adam.h,
Last reply from
adam.h,
Replies
2
Views
2,127

Advert