Hi,

We're re-wiring a flat that currently has a split load board with an off peak section for some convector heaters and 2 storage heaters. The off peak has its own meter that is radio controlled. We need to rewire the board and put the off peak into a separate board via a henley block, just wondered if this was just a case of taking the off peak supply into the new board and wire the rest as per usual, just wasn't sure how the meter situation worked?

Thanks

Ben
 
obviously the metering company would come out and make safe before they move the tails over to your new DB's.

gotta be careful with radio and timer meters.

could be working on something that's dead, next minute you know the timer kicks in and turns on the power to you unsuspectingly working on the circuit !
 

Similar threads

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
Rewire taking off peak into separate sub dis board
Prefix
N/A
Forum
UK Electrical Forum
Start date
Last reply date
Replies
1

Advert

Thread statistics

Created
jamminuk,
Last reply from
shocking_eg,
Replies
1
Views
1,952

Advert