Octopus
Ok. So I've got a job which has about 115 points in a large refurb/extension. The home owner is doing some of the work themselves and it's going to be spread over about 3 months....and a baby is due next month.... The agreement on invoicing is at each month end.
Part of the work has to be complete before another bit can start.
So I've been wondering how best to keep the invoicing simple and make sure I get a sensible payment each month?
I've only given a total price so would rather avoid going into too much detail with the client!
my only thought so far is 50% of the cost per point or new circuit done in each period for 1st fix and the same for 2nd fix, with the exception being the CU change which I would bill the day I do it!
any thoughts chaps?
Part of the work has to be complete before another bit can start.
So I've been wondering how best to keep the invoicing simple and make sure I get a sensible payment each month?
I've only given a total price so would rather avoid going into too much detail with the client!
my only thought so far is 50% of the cost per point or new circuit done in each period for 1st fix and the same for 2nd fix, with the exception being the CU change which I would bill the day I do it!
any thoughts chaps?