Hi wondered what your thoughts were.
We are installing a 40Kwp we have run a 95mm 4core swa from the main intake position to a 100 amp tp&n 4 Way three phase distribution board .
We are then using 2 x Triple pole mcb's to supply our two 17000TL Tripower Invertors.
I am not certain if we should be fitting our three phase self generation meter at The new three phase distribution Board Adjacenent to the inverters or at the origin of the new sub-main we have laid,
I would normally fit it at the origin , just keen to see what others think or are doing.
Thanks for you reply's
We are installing a 40Kwp we have run a 95mm 4core swa from the main intake position to a 100 amp tp&n 4 Way three phase distribution board .
We are then using 2 x Triple pole mcb's to supply our two 17000TL Tripower Invertors.
I am not certain if we should be fitting our three phase self generation meter at The new three phase distribution Board Adjacenent to the inverters or at the origin of the new sub-main we have laid,
I would normally fit it at the origin , just keen to see what others think or are doing.
Thanks for you reply's