Yes it's a chore this one. 30 year old MK unit with main switch and no RCDs in sight. 18 circuits and on every one the original installer thought he'd write the MCB rating and cable size, no other circuit info at all !
There are 5 rings, 2 cooker circuits, 2 immersions, 3 socket radials and 6 lighting circuits so to determine exactly what went where and test everything has been a full on and headache inducing day ! And there are a couple of dodgy readings to be investigated and resolved as well as installing the new board with 18 RCBOs tomorrow.
You see Domestic isn't always as easy as many are quick to say. :)
 
I have often quoted for 2 days labour on a few CU changes of late, when you walk in and see the age and nothing is identified or labelled. then you get a sixth sense for trouble ahead..
It can even be more simple things when house bashing that confuse things.. today I have been working out why the lights have failed in a garage, fed from house in T&E and a fcu but working out which circuit its off is a nightmare as the circuits all rewireables with no rcd in sight have been interconnected. turned everything off in the end and found out somehow under the floorboards its got 3 different circuits supply the damn garage!! its not all easy in the domestic sector...
 
30 year old MK unit with main switch and no RCDs in sight. 18 circuits and on every one the original installer thought he'd write the MCB rating and cable size, no other circuit info at all !
There are 5 rings, 2 cooker circuits, 2 immersions, 3 socket radials and 6 lighting circuits so to determine exactly what went where and test everything has been a full on and headache inducing day !

But finding out what they all do is very satisfying.

This is precisely why I simply don't believe a lot of EICR's are done in a decent way - as you point out determining what each circuit did took 1/2 day!
 
Well it's not done yet as the new board didn't turn up at my house until 4.30 today, luckily the customer was absolutely fine about it and I brought another job forward to do today. When it's done tomorrow I'll post up a before and after picture, it shouldn't look much worse after. :D Still got a high end to end on the lives of one ring to sort out though and a low N-E on the biggest lighting circuit in the place.:(
 
Had to have a last minute change of manufacturer too, with 18 RCBOs Hager was just too expensive so I was going for BG with the new compact RCBOs, but apparently there may be an issue and they're currently 'in quarantine' ?? Anyone on here ever tried a Niglon board ? :)
 
Well the two day job is turning into a three day job. :( Still tracking down a strange fault and my brain said enough at 6.30 today.

Nice update...an honest admission of how a job,and therefore a possible quote,can go awry,if you give a hoot :)

If it is any consolation,i have one now,where it should have been boxed up Wednesday,but i will be there again tomorrow :(

Client is right as rain,and has tardis pockets,but so far,3/4 of the installed gear is either wrong,broke or incompatible,and the "joiner" has made me think,just how bad does a tradesman have to be...before he is merely a vandal? :rolleyes:
 
It's finally all done. Found the dodgy end to end on the kitchen ring, a neutral/earth reversal on a light fitting-worked fine before with no RCDs/RCBOs in sight:D and two radials sharing very good continuity on the neutrals,both upstairs sockets so may once have been a ring but high Megohms across L-L and CPCs. This is now a 16a single radial with two cables at the RCBO. :) Customers were very happy and no quibble with paying extra for the fault finding, this job has left me knackered though.:rolleyes:
 
Had to have a last minute change of manufacturer too, with 18 RCBOs Hager was just too expensive so I was going for BG with the new compact RCBOs, but apparently there may be an issue and they're currently 'in quarantine' ?? Anyone on here ever tried a Niglon board ? :)

That's slightly concerning (about the BG compact RCBOs), I was going to order a board's worth next week. Anyone heard anything about this? The client has already declined a Hager board due to the £110 price difference.

What board did you go with, in the end?
 
That's slightly concerning (about the BG compact RCBOs), I was going to order a board's worth next week. Anyone heard anything about this? The client has already declined a Hager board due to the £110 price difference.

What board did you go with, in the end?

They got hold of a Niglon board for me in the end Steve, which arrived only just in time. Ok although the actual enclosure seemed a bit thin, and it had the mysterious twisting RCBOs which were impossible to keep properly vertical ! Also the covers always come off easy but once the board is loaded up and connected it's a fight to get it back. :rolleyes:
 
I used a Niglon RCBO board once about 10 years ago. The devices weren’t bad but the insulated enclosure was dreadful. Never used one again.
I’ve been using Lewden pre-loaded RCBO boards for a year or two now. Easily the most keenly priced units I‘ve come across. The devices are great; the metal enclosures are ok. Oddly enough MK metal enclosures seem to be the best but I can’t get on with the RCBOs, never mind the price. Hager are about the same as MK IMO, although they have recently brought out a reduced size RCBO up to 32A which was very useful in an existing 16th Edition board...
 

Reply to 2 day CU upgrade,a bit of a pain. in the UK Electrical Forum area at ElectriciansForums.net

Similar Threads

  • Locked
  • Sticky
Beware a little long. I served an electrical apprenticeship a long time ago, then went back to full time education immediately moving away from...
Replies
55
Views
5K
I installed outdoor lighting and outlets. I finished this past year. I passed my inspection on April 2022. I was so pleased, BUT now the circuit...
Replies
3
Views
908
Hi all, new to posting but been reading for years. I inherited a house from my grandmother who passed in 2021, I intend to renovate and rent out...
Replies
97
Views
10K
Currently quoting for a job that needs to be done next week and working out how best to proceed, so thoughts welcome. Current situation: -->PME...
Replies
6
Views
4K
Hi guys Been called to a doctors house recently....you know the type that have plenty of money but want to hold off on shelling out...
Replies
11
Views
9K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Electrical Forum

Welcome to the Electrical Forum at ElectriciansForums.net. The friendliest electrical forum online. General electrical questions and answers can be found in the electrical forum.
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock