Can anyone confirm/refute this for me?

Last week Western Power changed the mains head on a job I was doing. Two guys, working live, had a good chat with them about what they were doing, so I know they were.

This week, on another job, an Eon site surveyor tells me they don't do live work, and to change a mains head they have to dig up outside and it will involve interrupting the supply to the adjacent three premises ..... Same job, diffferent supplier.

Are they giving me the run around? Or do the different DNSs have their own policy?

Thank guys.
 
This is an old bakolite type three phase head, only one phase wired.

I've had it before where Western P have changed a three phase head working live. Are Eon trying to raise the cost by involving more work?
 
when the servce fuse started overheating at my mums i called e on out about it and switched off the power in all fairness they were there within 20 mins of ringing them they said that ive got 2 choices 1 they could dig up the cable and cut it or they could switch it of at the sub station i said switch it off at the substation

when they pulled the fuse the cut out was melted

i asked them if the dug up the cable what did they do with it they just told me that they remove the lead sheath then cut the conductors 1 by 1 then the joint them back together live
 
If its a rural location they are keen to lay cables in the ground rather then overhead now.To supply buildings.
Theres a scheme going around ours at the moment which makes it alot cheaper. If thats the case they will shut down the network. Eon might be trying to do that. The lines are 60+ old and the poles start to show signs of movement.
 
every DNO is different just as every situation is different My cable head would be a daudle to do live IMO but my mums would have to be killed hers is way under stair and very fragile bakalite old one its a case of Horses for Courses and the guy on the ground being "Responsable for his health and saftey and the health and saftey of those around him" ie its Up to guys on the job Management cant dictate to do it live
 
It could be then that the head's damaged then, it's certainly very old and possibly unstable to work on. Thanks for the info guys :).
 

Reply to Eon Don't Work Live??? in the Australia area at ElectriciansForums.net

Similar Threads

I had an interesting little job this morning. Three sockets in an extension were not working and haven't worked for quite some time (years). It...
Replies
0
Views
271
Been round to a house to quote to replace some storage heaters for new panel heaters and came across a strange (to me at least) way of wiring the...
Replies
23
Views
4K
This drives me round the twist, the client tells you what they want, kind of. you do the work the way the client asks you to and then when its all...
Replies
13
Views
2K
Good day I'm a university student on a product design course. To create a product around electricians day to day work making your lives easier...
Replies
20
Views
2K
Hey all, I'm looking for some advice to help me troubleshoot my strange issue with my consumer unit/fuse board on which my RCD keeps tripping...
Replies
25
Views
2K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock