A previous customer has asked us to install around 3kWp extension to a 3.75kWp (3.68 lim) system we installed on his house last summer. Exact size of the PV extension will be determined by the new roof on the property extension. The property has a single phase supply only. DNO has approved an additional 3kW and has said it is to be installed under G59-2.
We have not installed an extension before so how do we go about applying G59-2? the 3kW inverter will be G83. So do we need to install a G59 relay? I have heard this but never done it. Is it expensive? where is is fitted? Can anyone point me in the right direction please??!!!
We have not installed an extension before so how do we go about applying G59-2? the 3kW inverter will be G83. So do we need to install a G59 relay? I have heard this but never done it. Is it expensive? where is is fitted? Can anyone point me in the right direction please??!!!