Hi All
First time need your help with a G59 form, I have installed a 3-250kw Solaredge system last year, the customer has required us to install a new boiler Baxi Ecogen 1kw I have spoken to the DNO they have advised me to d a G59 application, do I need to do 2 G59 part 1a applications for each technology i.e. PV system, Baxi Ecogen and is this the only form I have to fill in.
Cheers Solar City for the G59 application PDF form help.
Many thanks
Paul
First time need your help with a G59 form, I have installed a 3-250kw Solaredge system last year, the customer has required us to install a new boiler Baxi Ecogen 1kw I have spoken to the DNO they have advised me to d a G59 application, do I need to do 2 G59 part 1a applications for each technology i.e. PV system, Baxi Ecogen and is this the only form I have to fill in.